How do I figure out how many tons of asphalt I need?

How do I figure out how many tons of asphalt I need?

Converting Your Calculation Into Tons to Get Your Asphalt Tonnage. Divide your findings by 2,000 (the number of lbs in a ton) to find your asphalt tonnage.

How many tons are in a square yard of asphalt?

1 cubic yard of hot asphalt mix weighs 2.025 tons or 4050 lbs. These measurements are an approximation and therefore when you are ordering the quantity ensure that you add more asphalt to gather for the waste and you don’t run short as you do your pavement project.

How many tons of asphalt can be placed in a day?

“Eight-foot pavers range in size from 12,000-25,000 lbs. and the smaller pavers can place 500-600 tons a day and the bigger 8-ft. machines can place 1,200-1,800 tons a day.”

How much does a ton of asphalt cover?

Asphalt cost per ton One ton of asphalt covers 30 to 80 square feet. A 2-car driveway needs 7.5 to 18 tons of asphalt, depending on the thickness.

How many sq ft are in a ton?

600 sq ft
Tonnage Table

Area (Square Feet): BTU Tonnage
600 sq ft 12,000 BTU 1 Ton
900 sq ft 18,000 BTU 1.5 Tons
1,200 sq ft 24,000 BTU 2 Tons
1,500 sq ft 30,000 BTU 2.5 Tons

What is hot mix asphalt?

Asphalt pavement refers to any paved road surfaced with asphalt. Hot Mix Asphalt (HMA) is a combination of approximately 95% stone, sand, or gravel bound together by asphalt cement, a product of crude oil. The resulting Hot Mix Asphalt is loaded into trucks for transport to the paving site.

How do you convert asphalt to tons?

  1. Area[SY] x Thickness[Inch] x 105 LBS / 2000 = Tons of GAB.
  2. 10 FT x 100 FT = 1,000 SQFT / 9 = 111 SY x 6 IN x 105 LBS / 2000 = 35 TONS.

How do you haul hot asphalt?

As previously stated, hot asphalt will begin cooling as soon as it’s deposited into the dump truck. As such, you, as the operator, must do all you can to keep it warm and mailable for a smooth delivery. One way to do this is by covering the top of the dump truck bed with a tarp or specially-designed cover.

How long can you work hot asphalt?

This doesn’t mean you need to avoid your parking lot or driveway during this time, however! Avoid driving on new asphalt for a full three days and up to a week in hotter temperatures; after that, you can use your new pavement for standard vehicle traffic even as the material continues to cure.

How much does hot mix asphalt cost?

Based on the above price: 2” or 50.8 mm thick = 24 SqM = A$7.40 / SqM+ GST. 4” or 101.6 mm thick = 12 SqM = A$14.80 / SqM + GST.

How many cubic feet are in a ton of asphalt?

For example, if the area is 40 cubic feet, then the formula is: 40 cubic feet x 148 PCF = 5,920 pounds of asphalt mix. Next, convert your pounds of asphalt mix value to tons. According to Asphalt Institute, 2,000 pounds equals 1 ton.

How many square feet does a 2 ton AC unit cover?

Units that are 2 tons can cool off 901-1200 square feet spaces. Units that are 2.5 tons can cool off 1201-1500 square feet, etc. This pattern continues up to units of 5 tons that cool off 2401-3000 square feet, with every half ton increase adding about an additional 300 square feet.